2025 - KYOGLE
Bonalbo
- .
- Pre-construction phase
- Bulk earthworks removal of material to specified design level
- Erosion and Sediment Control, the use of sand filled bulk bags and silt curtain to prevent contaminated materials spreading into creek
- Long reach excavator used to place rock at toe of batter
- Geofabric lined slip face with 300- 500mm rock placement for bank stabilisation
- 300-500mm rock placement on benched slip face
- Construction of access track fro pump station/ fabric lined rock mattress installation due to poor natural foundation
- Access track base layer compaction before density tests
- Installation of gabion rock filled reno mattress for bank stabilisation
- Access track formwork and steel installation
- Access track concrete pour
- Sprayed Emulsion for 2 coat seal
- Tippers spreading stone for 2 coat seal